Hock Lian Seng wins circle line Marina Bay station contract

The civil works contract (C901) for the Circle Line Marina Bay Station has been awarded to Hock Lian Seng Infrastructure (Pte Ltd).

The S$348.4 million contract is for the construction and completion of the Circle Line Marina Bay Station and tunnels.

It includes alteration and addition works to the current North South Line (NSL) Marina Bay station, diversions of the East Coast Parkway and demolition of a vehicular underpass.

The 2.4-kilometre extension will be fully underground and is scheduled for completion by 2012.

The Marina Bay station is a new station on the Circle Line.

It will be an interchange station that will connect the Circle Line to the present North South Line. – CNA/de

Source : Channel NewsAsia – 21 Feb 2008